Santa Clara Valley Water District, California, 2027-2031 Capital Improvement Plan (CIP) Alert
How Did Santa Clara Valley Water District’s Capital Spending Change Between the Last Two CIPs?
The Santa Clara Valley Water District capital improvement plan for 2027-2031 totals $3.00 billion. That is down $52.4 million (−1.7%) from the 2026-2030 plan’s $3.05 billion. The number of projects is unchanged at 76. For vendors tracking the Valley Water CIP, the headline is stability rather than retrenchment: the program keeps its size and its shape, and dam seismic retrofit projects and water infrastructure projects still make up most of the dollars.
Table 1. Santa Clara Valley Water District CIP, edition over edition
| Metric | 2026-2030 | 2027-2031 |
|---|---|---|
| Total CIP value | $3.05 billion | $3.00 billion |
| Distinct project count | 76 | 76 |
| Average project value | $40.2 million | $39.5 million |
Totals count only the dollars each plan programs in its own five years.
The small decline looks like re-phasing, not a smaller program. The project count is identical and the average project value slipped only from $40.2 million to $39.5 million. Some dollars have moved out of the five-year window rather than out of the plan.
Which Departments Saw the Largest Changes in Santa Clara Valley Water District’s CIP?
Table 2. Largest department moves, 2026-2030 vs. 2027-2031
| Department | 2026-2030 | 2027-2031 | $ change | % change |
|---|---|---|---|---|
| Flood Protection | $564.1 million | $521.1 million | −$43.0 million | −7.6% |
| Water Supply | $2.36 billion | $2.34 billion | −$23.3 million | −1.0% |
| Water Resources Stewardship | $52.1 million | $75.0 million | +$22.9 million | +43.9% |
| Buildings & Grounds | $38.8 million | $29.4 million | −$9.4 million | −24.3% |
| Information Technology | $39.0 million | $39.5 million | +$0.5 million | +1.2% |
Figures are the plan’s own department totals over each plan’s own years.
Flood Protection drove most of the overall decline, falling $43.0 million. Water Supply, still by far the largest department at $2.34 billion, eased by $23.3 million. Water Resources Stewardship moved the other way, growing 43.9% to $75.0 million. That is a signal for habitat, fish passage and mitigation specialists watching the Valley Water CIP.
What Are the Largest Projects in Santa Clara Valley Water District’s 2027-2031 CIP?
- Anderson Dam Seismic Retrofit (C1): $1.02 billion (Dams, Levees, Stormwater and Flood Control). The project plans, designs and builds improvements to Anderson Dam to address seismic performance concerns and rehabilitate aging appurtenant facilities, including replacing most of the existing embankment with a well-compacted, zoned embankment designed to withstand the Maximum Credible Earthquake.
- RWTP Reliability Improvement: $231 million (Drinking Water Treatment). The project builds new facilities at the Rinconada Water Treatment Plant, including a new filter building and raw water ozonation, and raises plant capacity from 80 million to 100 million gallons per day.
- Coyote Creek, Montague Expressway to Tully Road (E1): $214 million (Dams, Levees, Stormwater and Flood Control). The project improves about nine miles of Coyote Creek to reduce the risk of flooding to homes, schools, businesses and highways from a 20-year flood event like the one in February 2017.
- Pure Water Silicon Valley - Full-Scale Direct Potable Reuse (DPR) Facility: $146 million (Drinking Water Treatment). The facility will sit next to the Silicon Valley Advanced Water Purification Facility in San José and will be able to produce up to 24,000 acre-feet per year of purified water originating from the San José Regional Wastewater Facility.
- Calero Dam Seismic Retrofit - Design & Construction: $134 million (Dams, Levees, Stormwater and Flood Control). The project designs and builds improvements to Calero Dam to stabilize the embankment against a Maximum Credible Earthquake, modify or replace inadequate outlet works, and modify the spillway or increase freeboard so the dam can safely pass the Probable Maximum Flood.
How Is Santa Clara Valley Water District’s CIP Governed and Approved?
Valley Water staff prepare the five-year CIP each year. The Board’s Capital Improvement Program Committee reviews the preliminary plan before the full Board of Directors acts on it [4]. The committee also keeps a standing annual work plan and reviews it throughout the year [3]. Each year the Board approves changes, additions and deletions to the previous year’s CIP. It then has further chances to direct individual projects as they move through planning, design and construction [1].
The CIP is adopted in May and reflects planned schedules and expenditures for the coming fiscal year [2]. For the 2027-2031 plan, Valley Water said the Board would close the public hearing on May 12, 2026, when staff were to present the final five-year plan together with the biennial budget [5]. The provided sources do not confirm the date of the final vote.
What Is the History of Santa Clara Valley Water District and Its Infrastructure?
Valley Water was founded in 1929 in response to overdrawn groundwater basins, land subsidence and the need for central water management [6]. Its predecessor, the Santa Clara Valley Water Conservation District, began building dams during the Great Depression and completed Calero, Guadalupe and Almaden dams in 1935 [7]. Today the district manages water for Santa Clara County’s roughly 2 million residents [8]. Its mission covers safe drinking water, flood protection and stream stewardship [6].
The district’s major systems include 10 reservoirs holding about 170,000 acre-feet, of which Anderson is the largest [7]. It also runs three water treatment plants with up to 220 million gallons a day of capacity and the 8-million-gallon-a-day Silicon Valley Advanced Water Purification Center. It recharges groundwater through percolation ponds and streambeds and manages 333 miles of creeks [6].
Fun Facts About Santa Clara Valley Water District
- Santa Clara County is one of California’s 27 original counties, established on February 18, 1850, at statehood [9].
- The county takes its name from Mission Santa Clara de Asís, founded in 1777 as the eighth mission in California and named for Saint Clare of Assisi [10].
- San Jose was California’s first state capital; the first California State Legislature met there on December 15, 1849 [10].
- Santa Clara College was founded on the mission grounds in 1851 and is described as the first institution of higher learning in California [11].
- Before the tech era, orchards of apricots, cherries and prunes earned the area the nickname “Valley of Heart’s Delight.” It was later known as Silicon Valley [11].
- Lick Observatory, operated by the University of California, sits on Mount Hamilton near San Jose [13].
- The New Almaden quicksilver (mercury) mines are California Historical Landmark No. 339. They were named for the mining town of Almadén in Spain, and the former mines are now part of the roughly 4,163-acre Almaden Quicksilver County Park [12].
- The Winchester Mystery House, a Victorian mansion at 525 S. Winchester Blvd. in San Jose, is California Historical Landmark No. 868 [12].
How FirmoGraphs Can Help?
FirmoGraphs tracks public capital improvement plans and flags edition-over-edition changes like this one. That helps A/E firms, contractors and vendors see where agencies are moving money, from dam seismic retrofit projects to water infrastructure projects, and engage early. Learn more at FirmoGraphs.
References
Notebook (agency documents): [1] 2027–2031 Five-Year Capital Improvement Program, Overview, “Opportunities for Board Direction on Capital Projects” — notebook — 2027–2031 Five-Year Capital Improvement Program (cip), page 8 [2] Board Agenda, Safe, Clean Water program audit findings (CIP adopted in May) — notebook — Agenda (board), page 117 [3] Capital Improvement Program Committee Agenda, August 17, 2026 — notebook — Agenda – 2026-08-17 (board), page 5
Web sources: [4] Capital Improvement Program (CIP) Committee, December 15, 2025 approved minutes — web — https://assets.valleywater.org/files/12152025%20Approved%20CIP%20Meeting%20Minutes.pdf [5] Valley Water’s annual Capital Improvement Program projects to reduce flood risk — web — https://valleywaternews.org/2026/01/23/valley-waters-annual-capital-improvement-program-projects-to-reduce-flood-risk [6] About Valley Water — web — https://www.valleywater.org/about [7] Local Dams and Reservoirs — web — https://www.valleywater.org/your-water/local-dams-and-reservoirs [8] Where Does Our Water Come From — web — https://assets.valleywater.org/files/2022%20Where%20Does%20Our%20Water%20Come%20From.pdf [9] History of Santa Clara County, California — web — https://en.wikipedia.com/wiki/History_of_Santa_Clara_County,_California [10] Santa Clara County, California — web — https://www.wikiwand.com/en/Santa_Clara_County,_California [11] History — Discover Santa Clara — web — https://www.discoversantaclara.org/history/ [12] California Historical Landmarks in Santa Clara County — web — https://www.wikiwand.com/en/articles/California_Historical_Landmarks_in_Santa_Clara_County [13] List of attractions in Silicon Valley — web — https://www.wikiwand.com/en/articles/List_of_attractions_in_Silicon_Valley
Frequently asked questions
- What is the total of the new Santa Clara Valley Water District capital improvement plan?
- The 2027-2031 plan totals $3.00 billion across 76 projects, counting only dollars programmed within its own five fiscal years.
- How much did the Valley Water CIP change from the prior edition?
- It fell $52.4 million (−1.7%) from the 2026-2030 plan's $3.05 billion, with the same 76 projects.
- What are the biggest projects?
- The Anderson Dam Seismic Retrofit leads at $1.02 billion, followed by the RWTP Reliability Improvement ($231 million) and Coyote Creek, Montague Expressway to Tully Road ($214 million). Dam seismic retrofit projects at Calero and Guadalupe dams also rank among the largest.
- Which areas grew most?
- Water Resources Stewardship grew most, rising 43.9% to $75.0 million. Information Technology edged up 1.2% to $39.5 million, while Flood Protection fell $43.0 million.
- When was the plan adopted?
- The Board of Directors adopts the CIP each May. For this edition the public hearing was scheduled to close on May 12, 2026, alongside the biennial budget [5]. The final vote date is not confirmed in the provided sources.